HOW TO PREPARE METHODOLOGY OR METHOD STATEMENT OF CONSTRUCTION WORK

Here I am going to discuss how to prepare a method statement for construction activities step by step:



Content :- In this with we write the content which included in the document serial wise.

  1. PURPOSE
  2. SCOPE
  3. RESPONSIBILITY
  4. CONTROLLING SPECIFICATION
  5. MATERIAL
  6. TOOLS & TACKLES
  7. PROCEDURE
  8. INSPECTION
  9. DOCUMENTATION


1. PURPOSE:- In this we write the purpose of the procedure which includes all activities.


2. SCOPE:- In this we write about the scope of the work, which includes activity name and name of part of construction work.


3. RESPONSIBILITY:- We include the persons who are responsible for the the activity such as project manager, engineer, supervisor.


4. CONTROLLING SPECIFICATION:- In section we include which standards and specification are used for the activity.


5. MATERIAL:- In this we include the the all kind of materials used for the work with name of material and brand.


6. TOOLS & TACKLES:- In this we include name of the tools and tackles used for the work or activity.


7. PROCEDURE:- In this section we include the procedure of the work. Preconditioning of the work, during activity and application of the material  and tools, and after completion of work.


8. INSPECTION:- In this section we include the inspection procedure of work by checked by QC in charge and checklists of the work and activity.


9. DOCUMENTATION:- In this section we include the documents formats which used for the activity.